CORONATION CONCERT
Power Logistics provided sustainable show, site and broadcast power solutions for the Coronation Concert held at Windsor Castle in May 2023.
- Project management
- Site, show and broadcast power
- Power monitoring and auditing
- 160kWH batteries to minimise fuel usage
- 45Kwh batteries were also utilised at the accreditation gates
- 13km of cable
- 150 distribution units
- 400m of DDA compliant cable ramp
- 2.3km of festoon lighting
Results
- 20,000 litres of fuel saved
- 832Kwh of battery energy storage deployed
D-DAY 80
Power Logistics delivered a comprehensive and sustainable power solution to the D-Day 80 commemorative events held in both Portsmouth and Normandy.
- Project management
- Site and show power
- Power monitoring and auditing
- Battery energy storage system for the full five weeks the production team were onsite
- Grid power
- Green D+ HVO used site wide
- Solar powered fuel bowsers
- LED site lighting
- Dusk to dawn sensors
- Hydrogen power introduced in 2024
Results
- 20,000 litres of fuel saved
- 832Kwh of battery energy storage deployed
PLATINUM JUBILEE CELEBRATIONS
Power Logistics was incredibly proud to deliver site, show and broadcast power to HM The Queen’s Platinum Jubilee Celebrations across the long weekend of 2nd – 5th June 2022.
- Implemented a comprehensive plan for the delivery of a sustainable electrical solution
- Sustainability was at the forefront of the project
- On-site at Buckingham Palace for several weeks
- Battery energy storage systems
- Site lighting including LED towerlights and 100s of metres of festoon, house nd emergency lighting, along with LED illuminated signage
- Battery packs for the Jubilee Pagaent
- Green D+ HVO
- Grid power
- DDA compliant cable ramp
Results
- Cost efficiencies
- CO2 reduction by 90%*
- Reduced number of generator farms