CASE STUDIES

CORONATION CONCERT

Power Logistics provided sustainable show, site and broadcast power solutions for the Coronation Concert held at Windsor Castle in May 2023.

 

  • Project management
  • Site, show and broadcast power
  • Power monitoring and auditing
  • 160kWH batteries to minimise fuel usage
  • 45Kwh batteries were also utilised at the accreditation gates
  • 13km of cable
  • 150 distribution units
  • 400m of DDA compliant cable ramp
  • 2.3km of festoon lighting

 

Results

  • 20,000 litres of fuel saved
  • 832Kwh of battery energy storage deployed

CREAMFIELDS

Power Logistics has been delivering sustainable temporary power solutions to Creamfields since 2021, delivering a comprehensive project management and consultancy service to the festival, including all site and show power, along with site lighting.

 

  • Project management
  • Site and show power
  • Power monitoring and auditing
  • 100 generators – 20 kVa to 550 kVa
  • 25km of LED festoon lighting
  • 100 towerlights
  • 300kw batter ypacks for crew catering, camping, bunkabins and tour buses
  • Green D+ HVO

 

Results

  • Reduction in the event’s carbon footprint
  • Data analysis to optimise power solution for future events

RADIO 1 BIG WEEKEND

Power Logistics has been delivering sustainable power solutions to Radio 1’s Big Weekend since 2019.

 

  • Project management
  • Site and show power
  • Power monitoring and auditing
  • Implementation of an advanced energy management strategy
  • Battery technology
  • Green D+ HVO used site wide
  • Solar powered fuel bowsers
  • LED site lighting
  • Dusk to dawn sensors
  • Hydrogen power introduced in 2024

 

Results

  • 61% reduction in fuel since 2019
  • 62% reduction hours since 2019
  • 119% increase kwh since 2019

CORONATION OF TM KING CHARLES III AND QUEEN CAMILLA

Power Logistics delivered a comprehensive and sustainable power solution to both the ceremonial elements and live broadcast from Westminster Abbey of the Coronation of TM King Charles III and Queen Camilla in London.

 

  • Project management
  • Meticulous planning
  • Broadcast power along the processional route, Canada Gate, Green Park
  • Audience welfare, security points, LED screens, control tent
  • Stage V generators sets
  • 26 batteries ranging from 15kWH – 422Kwh deployed
  • Cabling and distribution equipment
  • DDA compliant cable ramp

 

Results

  • 98415 Kg C02e saved by using GreenD+ HVO fuel
  • 2690 Expected hours saved due to use of BESS
  • Largest deployment of batteries at a major event in London

D-DAY 80

Power Logistics delivered a comprehensive and sustainable power solution to the D-Day 80 commemorative events held in both Portsmouth and Normandy.

 

  • Project management
  • Site and show power
  • Power monitoring and auditing
  • Battery energy storage system for the full five weeks the production team were onsite
  • Grid power
  • Green D+ HVO used site wide
  • Solar powered fuel bowsers
  • LED site lighting
  • Dusk to dawn sensors
  • Hydrogen power introduced in 2024

Results

  • 20,000 litres of fuel saved
  • 832Kwh of battery energy storage deployed

BST HYDE PARK

Power Logistics has been providing a complete project management solution for AEG’s BST Hyde Park festival, held in London’s Hyde Park, since 2014. This includes the delivery of all site and show power and site lighting requirements, including: all stages, back stage and production areas, the VIP gardens, numerous bars and concessions and brand activation areas around the site.

 

  • Project management
  • Sustainable solutions and innovation
  • Green D+HVO site wide
  • Battery technology
  • Power monitoring
  • Implementing an energy management system

 

Results

  • 30% reduction in fuel consumption
  • Despite an additional show weekend being added in 2022 fuel usage remained consistent
  • Number of Kw/H increased from 2.12 Kw/H to 2.98 Kw/H in 2023

PLATINUM JUBILEE CELEBRATIONS

Power Logistics was incredibly proud to deliver site, show and broadcast power to HM The Queen’s Platinum Jubilee Celebrations across the long weekend of 2nd – 5th June 2022.

 

  • Implemented a comprehensive plan for the delivery of a sustainable electrical solution
  • Sustainability was at the forefront of the project
  • On-site at Buckingham Palace for several weeks
  • Battery energy storage systems
  • Site lighting including LED towerlights and 100s of metres of festoon, house nd emergency lighting, along with LED illuminated signage
  • Battery packs for the Jubilee Pagaent
  • Green D+ HVO
  • Grid power
  • DDA compliant cable ramp

 

Results

  • Cost efficiencies
  • CO2 reduction by 90%*
  • Reduced number of generator farms

WINTER WONDERLAND

Power Logistics has been the official power provider to the globally renowned Winter Wonderland in London’s Hyde Park for 15 years.

 

  • Full project management
  • Sustainable and innovative solutions
  • Supply, install and maintenance of generators
  • Cabling and distribution equipment
  • LED lighting solutions
  • Engineers onsite for six week open period
  • Power monitoring
  • Green D+ HVO site wide
  • Battery technology

 

Results

  • Cost efficiencies
  • CO2 reduction by 90%*
  • Reduced number of generator farms

EXTREME E

Power Logistics designed and implemented a bespoke Energy Management Solution to meet the requirements of global sustainable motorsport series Extreme E since its inception.

  • Project management
  • Site and show power
  • Power monitoring and auditing
  • Implementation of an advanced energy management strategy
  • Battery technology
  • Solar power
  • LED site lighting
  • Dusk to dawn sensors

 

Results

  • By race 4 of season 2 fuel consumption had been reduced by 40% from the first race in the first season, despite energy consumption increasing by 41%.
  • Entire site ran on solar energy for an 11-day period with four solar and battery systems distributed around the site generating the power
  • Solar panels delivering 5 megawatt hours per race which is the equivalent to saving 2000 litres of fuel
  • Events are now powered by 90% renewable energy

JOCKEY CLUB

Power Logistics has been providing site, hospitality and broadcast power to the Jockey Club’s flagship events since 2012. This includes supplying all generators, cabling and distribution equipment and site lighting for the Cheltenham Gold Cup, Epsom Derby and Grand National at Aintree. 

  • Longstanding contract
  • Accurate specification, delivery, installation and commissioning of generators and power distribution services
  • Fuel management
  • Generators range from 30kVA – 2000Kva
  • Utilise grid power wherever possible
  • Wireless light switches

Results

  • Close working relationship ensures continuity of our delivery of services between all racecourses
  • Extensive power monitoring has reduced fuel usage and carbon emissions

AWARDS & ACCREDITATIONS

logo logo logo logo logo logo logo logo logo